This Saturday, October 31, the Grand Haven Farmers Market wraps up its 2026 season at Chinook Pier, 301 N. Harbor Drive, from 8 a.m. to 1 p.m. The Wednesday market has already ended for the season. Changes are ahead for the waterfront, with the Chinook Pier redevelopment planned to break ground in spring 2027 and the North Pier across the channel closed since April for reconstruction.

Each waterfront project is on its own schedule, and those schedules now overlap until 2028. Here's how they line up and what that means for a regular week in town this winter.

The market stayed one more season

Earlier plans called for the farmers market to temporarily relocate from Chinook Pier to Mulligan’s Hollow after the Coast Guard Festival, with a return planned for 2028, according to FOX 17.

With redevelopment now scheduled to begin in 2027, the market remained at its familiar waterfront location for the full 2026 season, as the Grand Haven Tribune reported.

Details about the market’s 2027 location are still to come. Visit the Grand Haven Farmers Market website for updates as the spring season approaches.

What's planned for Chinook Pier

Grand Haven's Planning Commission approved the site plan on August 11. According to WGVU, the $10 million project covers three acres along the north side of the waterfront walkway. It includes restaurant, retail and office space, public green space and a gas fire pit. Grand Rapids-based CopperRock Construction is leading the project.

The detail that matters most for market regulars is a new multipurpose building. CopperRock senior development specialist Greg Taylor told WGVU it would have "interior and limited exterior farmer's market utility." It will also double as covered parking when the market isn't running. That means the market's eventual home will have a roof and indoor space, which an open lot on Harbor Drive can't offer.

The reported project estimate has changed. When the City Council approved a ground lease with CopperRock in September 2025, WGHN reported estimates of $15 million to $20 million. The plan approved this August is listed at $10 million. Planning commissioner Amy Kozanecki called it "a vast improvement over the plan two months ago" and "a great balance of open space and development."

A few pieces aren't settled yet. The commission's approved minutes made approval conditional on later sign-off for exterior materials and a final location for the mini-golf course. Lighting, landscaping and signage also still need to be finalized. CopperRock plans to break ground in the spring, and construction could take up to 18 months. If work starts on schedule, construction could wrap up in fall 2028, around the same time the North Pier is expected to reopen.

The North Pier is closed until late 2028

The north side of the channel is already under construction. The North Pier is reached from North Shore Drive in Ferrysburg. Since April, it has been part of a U.S. Army Corps of Engineers rebuild. The website, Visit Grand Haven's July 2026 update, says pedestrian access is expected to stay closed until late 2028. A Coast Guard Local Notice to Mariners names Great Lakes Dock & Materials, L.L.C. as the contractor.

The scope is large. FOX 17 reported that a roughly 325-foot section of the pier will be demolished and replaced in part with a wave attenuator. Liz Wilkinson, the Corps' Grand Haven operations manager, told the station that "the last major maintenance at the North pier for Grand Haven was in the 1950s." The cost has also gone up. WGHN put it at $8.25 million in March, and Visit Grand Haven's July update lists $9.25 million.

MLive reported when the work happens. Construction runs 7 a.m. to 7 p.m., seven days a week. It stops in winter, in rough weather and during the Coast Guard Festival. Channel work is also restricted from March through June in 2027 and 2028, and MLive said completion could slip into summer 2028. So the coming winter should be the quietest stretch along North Shore Drive until the project ends.

North Beach Park is nearby at 18775 North Shore Drive. Ottawa County's park page still lists the beach and the dune stairs and overlook, with no construction closure posted.

Where each waterfront project stands

Place

Status as of late October 2026

Expected end

North Pier, Ferrysburg side

Closed to pedestrians since April

Late 2028

Chinook Pier

Market's last 2026 Saturday is Oct. 31; site plan approved

Groundbreaking in spring, then up to 18 months

South Pier and lighthouse

Armor-stone repairs finished in July

Work complete

Lighthouse Connector Park boardwalk

Repairs scheduled to finish the week of Oct. 12

Watch for fencing near the work areas

The South Pier is the steady piece. The Corps placed about 300 tons of armor stone at the south pierhead in July. WGHN reported on July 13 that the work was done, the temporary pedestrian closure had ended and lighthouse tour hours were not affected.

On the boardwalk, the City's September 17 notice said Lighthouse Connector Park repairs would start that day and finish the week of October 12. The City put temporary fencing around the work areas. The Tribune described the repairs near the Pier Peddler and closer to the state park entrance.

Winter Brings Changes to Grand Haven

Several recent openings and upcoming projects are bringing changes to Grand Haven, from downtown Washington Avenue to Beechtree Street and Robbins Road.

  • The Slice Shoppe opened at 38 Washington Ave. this summer, serving New York-style pizza. The Tribune covered the opening.
  • Cowan's Cafe is the new name for Rainy Days Cafe at 121 N. Beechtree St. The owners told the Tribune that the name is the only change.
  • 123 Washington Ave. is a vacant building that will be rehabilitated into first-floor commercial space, three two-bedroom apartments and a shared rooftop patio. That's according to an October 8 Michigan Economic Development Corporation release. The developer says the commercial space will be a restaurant, though no name has been announced.
  • Casey's has started building a convenience store and gas station at 1102 Robbins Road. The Tribune reports it's aiming to open in early 2027.

The fall and holiday calendar also stays mostly downtown, much of it within a few blocks of Washington Avenue:

  1. Saturday, Oct. 31, 5:30 to 7 p.m. The City's Haunted Haven indoor trick-or-treat at Central Park Place. That's the evening of the market's last Saturday.
  2. Saturday, Nov. 14, 9 a.m. to 3 p.m. The Holiday Craft & Artisan Market at Central Park Place, 421 Columbus Ave., with 57 makers and vendors listed on the City's calendar.
  3. Friday, Nov. 20, 5 to 8 p.m. Holiday Light Night on Washington Avenue, the downtown lighting that kicks off the holiday season.
  4. Saturday, Nov. 28, 6 to 8 p.m. Across the river, the Spring Lake Sparkle Kickoff at Epicurean Village, 110 W. Savidge St., with a lighting ceremony, choir concerts and Santa. After that, Santa in the Workshop runs at the same spot every Thursday, Friday and Saturday from Dec. 3 through Dec. 19. The listed hours for the Dec. 3 to 5 dates are 5 to 8 p.m.
  5. Saturday, Dec. 5. The Coast Guard Festival's Jingle Bell Parade.

There’s still plenty to enjoy around Grand Haven while waterfront construction moves forward, including downtown shopping, seasonal events and the South Pier.

As a Grand Haven native, I love my hometown and keep up with the latest happenings along the lakeshore. If you have questions about what these changes could mean for your home or future plans, reach out to me here, Jackson Properties Group. I'm always here to help!

Work With Julie

With deep roots in West Michigan and a home and investment properties in Grand Haven, Julie has a strong connection to the lakeshore and the communities she serves. She believes lasting relationships begin with honest guidance, thoughtful service, and follow-through.

Follow Me on Instagram